PROJECTS
ARK Power Solutions Private Limited

"An ISO: 9001- 2015 Company"

REFURBISHMENT & MODERNIZATION

 REFURBISHMENT & MODERNIZATION
PROJECTS UPTO 220 KV ELECTRICAL SUBSTATIONS
  • Detailed Project Report incorporating latest Industry Trends, increasing dependence, Feasibility Study, Cost of Project, Break Even Analysis preparation.
  • Supply, deliver, install, erect, test and commission equipment for upgrading old substations.
  • Aged electrical equipment will be replaced with more reliable switching, control and protection equipment based on the latest technology ensuring a reliable, secure and safe network.
  • Delivering modern, functional, and unique electrical solutions to our customers presently using old substations.
  • Increasing rating and adding additional feeders to the existing substations.
  • ERECTION, TESTING & COMMISSIONING

    PROJECTS UPTO 220 KV ELECTRICAL SUBSTATIONS
    Pre-Erection Activities
  • Preparation of a plan to carry out erection work and sequence of different activities.
  • Preparation for site storage and pre-assembly of the equipment, construction of roads, accesses for delivery of plant to the assembly area.
  • Erection of temporary structures, living quarters necessary for carrying out site work smoothly and speedily.

  • Erection of built-in parts & main operating components
  • Plan out erection work and sequence of different activities and ensure that the work at site is done as per the safety norms
  • Erection of HT / LT panels, transformer, other electricals and UG cables.

  • Testing & Commissioning
  • All the essential tools & tackles, latest testing kits are available with us with skilled workers, technical staffs, engineers and management for all aspects of etc.
  • Back to Top